PUC hears BAWSCA and RBOC updates as staff set to launch bond expenditure audits and follow up on two critical water projects
Summary
The Revenue Bond Oversight Committee summarized its 2018 work and an RFQ for third‑party expenditure audits; BAWSCA briefed commissioners on two remaining WSIP projects — Alameda Creek recapture and regional groundwater storage — and asked for PUC written updates when draft documents and yield estimates are available.
Get email alerts on the Water Supply Wsip topic
No spam. Unsubscribe anytime.
Travis George, chair of the Revenue Bond Oversight Committee, presented the committee's annual report to the San Francisco Public Utilities Commission, outlining the RBOC's 2018 activities and plans for 2019. George said the committee created a fund balance management policy and will issue an RFQ to select a third‑party contractor to conduct expenditure audits of various bond series, work expected to continue into 2020 and possibly 2021.
In a related update, the Bay Area Water Supply and Conservation Agency (BAWSCA) representative reviewed Water System Improvement Program progress and emphasized two remaining projects critical to water supply reliability: the Alameda Creek recapture project (estimated yield roughly 7,000 acre‑feet per year) and the regional groundwater storage and recovery project. BAWSCA said a revised draft EIR is in circulation for Alameda Creek recapture and requested that PUC staff provide a written report on whether project scope revisions are necessary. For the groundwater project, BAWSCA noted staff changes to well counts and design and said the promised yield analysis had not yet been provided; BAWSCA asked for the updated information and for the PUC to provide a written status report after internal meetings.
Commissioners asked for charts and comparative data on per‑agency monthly water use and urged staff to ensure up‑to‑date yield estimates are shared with the Commission. The RBOC's planned expenditure audits are intended to increase transparency around bond proceeds and capital spending and the committee extended its sunset date to 2025 to continue oversight work.
What happens next: staff will prepare the RFQ for bond expenditure audits, complete the technical yield analysis for the groundwater project, and provide the commission with written updates on Alameda Creek recapture and groundwater storage yields when the documents are available.