Walnut Street Phase 3 change order adds $36,373.39 after field conflict discovered
Evansville Board of Public Works · July 18, 2024
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.
Summary
The board approved Change Order No. 5 for the Walnut Street Phase 3 project, increasing the contract by $36,373.39 (new total $21,343,542.86) and adding three calendar days after water lines were found in planned storm sewer locations.
The Board of Public Works on July 18 approved Change Order No. 5 for the Walnut Street Phase 3 construction contract, increasing the contract price by $36,373.39 to a new total of $21,343,542.86 and adding three calendar days to the…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat
30-day money-back on paid plans