Citizen Portal
Sign In

Get Full Government Meeting Transcripts, Videos, & Alerts Forever!

Get email alerts on the Capital Projects topic

No spam. Unsubscribe anytime.

Walnut Street Phase 3 change order adds $36,373.39 after field conflict discovered

Evansville Board of Public Works · July 18, 2024
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The board approved Change Order No. 5 for the Walnut Street Phase 3 project, increasing the contract by $36,373.39 (new total $21,343,542.86) and adding three calendar days after water lines were found in planned storm sewer locations.

The Board of Public Works on July 18 approved Change Order No. 5 for the Walnut Street Phase 3 construction contract, increasing the contract price by $36,373.39 to a new total of $21,343,542.86 and adding three calendar days to the project timeline.

City engineering staff said crews discovered existing water lines located where storm sewers were planned, requiring field modifications to 10 structures. "As we were constructing several side streets, we needed some modifications because water lines were found to be where the storm sewers were planned to be," the city engineer said. The change order covers the contractor costs to make those modifications and to keep work moving.

The board moved, seconded and approved the change order by voice vote. No board member raised substantive objections during discussion.

Next steps: the contractor will implement the changes and the city will account for the additional cost and time in project records.