Board signs change order increasing East Side drainage project by $1.01 million
Summary
City engineers told the board that jurisdictional reviews prompted changes to materials and quantities, increasing the East Side drainage improvement contract by $1,010,997 to a new total of $3,714,060; the board approved the change order.
Get email alerts on the Infrastructure Change Order topic
No spam. Unsubscribe anytime.
The Evansville Board of Public Works on Nov. 7 approved Change Order No. 1 for the East Side drainage improvement project (23‑024), increasing the contract by $1,010,997 to a revised total of $3,714,060.
City engineering staff said multiple jurisdictional reviews — including the U.S. Army Corps of Engineers, U.S. Fish and Wildlife Service and the railroad — required changes in materials, methodologies and quantities that drove the increase. Engineers told the board that railroad permitting remained the principal outstanding clearance, and that they estimate about 92% of required reviews are complete.
The board voted to approve the change order by voice vote. Staff indicated the revised contract amount will be administered under the city’s construction contract procedures and noted remaining coordination with the railroad.
Next steps: staff will finalize change‑order paperwork and continue jurisdictional coordination required for project construction.