Jefferson County approves rebuild of landfill compactor after staff briefing on costs and risks
Summary
Commissioners approved a full rebuild of the landfill compactor with Western States, accepting an estimated cost of about $599,997 while noting possible variance, optional line items and a 90-day parts lead time and 2–2.5 month turnaround.
Get email alerts on the Solid Waste topic
No spam. Unsubscribe anytime.
Jefferson County commissioners voted July 8 to move forward with a full rebuild of a land‑fill compactor, accepting a Western States estimate of roughly $599,997 and staff assurances that the machine will be returned with a multi‑year warranty.
The board’s discussion focused on cost drivers and uncertainty. Western States personnel explained the quote includes standardized estimates for transport and salvage segments that can vary by location, and staff warned there is a potential variance—roughly a $50,000 contingency was discussed—with isolated scenarios that could increase costs further if hidden damage is discovered during disassembly.
County members pressed staff on optional items and recurring costs: painting the machine was estimated at $18,000, hauling estimates vary by region in the vendor’s pricing model, and the warranty line item is listed at $40,600 before vendor-provided credits and parts discounts. Western States told the board parts fulfillment would take about 90 days after order placement and the physical rebuild about two to two-and-a-half months, placing completion in December–January if the board approved immediately.
Commissioners said the rebuild was budgeted in the repairs line and concluded that a rebuild offered substantial lifecycle savings compared with buying new equipment (vendor estimates compared the rebuild to a new unit priced near $1 million). An unidentified commissioner moved to approve the rebuild estimate and the motion was seconded; the roll call was requested in the meeting record. The transcript does not record a detailed named vote tally in the public record excerpt.
The board instructed staff to capture final measurements, to proceed with vendor coordination, and to carry the item into next year’s repair budgets where necessary. The county will receive a five‑year/8,000‑hour warranty at completion, per the vendor’s estimate.