Port staff reported that six infrastructure projects supporting the America's Cup are on schedule and fully funded, Turner Construction will start major pier work this summer, and the Port's biannual contracting report recorded roughly $19 million in contracting activity and 28% LBE participation for the period reported.
Port staff told the commission that the infrastructure work tied to the America’s Cup is proceeding on schedule and is fully funded, while the Port’s biannual contracting report summarized contracting activity and emerging local‑hire data.
Joe Roget, a port structural engineer, said Turner Construction finalized amendment No. 4 and will begin construction on Pier 30/32 Phase 1 the week following the meeting. Turner was also scheduled to start Pier 29 substructure repairs and to demolish Pier 1½ on specified July dates; staff said six…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat