Get Full Government Meeting Transcripts, Videos, & Alerts Forever!
Get email alerts on the Pier 70 topic
No spam. Unsubscribe anytime.
Commission authorizes exclusive negotiations for Pier 70 historic buildings and approves Pier 70 shore-side power as CEQA mitigation
Summary
The commission authorized exclusive negotiations with Orton Development for Twentieth Street historic buildings at Pier 70, and approved a shore-side power project at Pier 70 (Resolution 1219) to mitigate air-quality impacts while Pier 27 shore power is decommissioned for cruise terminal construction; staff described financing that includes port capital, a 4'/kWh equipment charge and PUC rebates.
Get email alerts on the Pier 70 topic
No spam. Unsubscribe anytime.
The Port Commission authorized staff to enter exclusive negotiations with Orton Development for a development opportunity on the Twentieth Street historic buildings at Pier 70 and approved terms to implement a shore-side power project at Pier 70 as CEQA mitigation for the Pier 27 cruise-terminal construction.
Kathleen Dyhepp, Pier 70 project manager, summarized an extensive outreach and marketing process: 176 parties toured the buildings, 15 responses to a request for interest, four RFP proposals, then two finalists after withdrawals. Staff told commissioners the primary distinction between finalists was economic feasibility: Orton proposed to commit more equity and pursue a loan model, while the other team identified a feasibility gap and sought subsidies. Staff recommended authority to enter exclusive negotiations with Orton; commissioners approved the resolution to negotiate (Resolution 12-18).
Separately, Brad Benson and Kathleen Dijap presented a shore-side power project at Pier 70 intended to offset air-quality impacts caused when the Pier 27 shore-power facility must be decommissioned for terminal construction (the existing Pier 27 shore-power facility had been funded by a combination of BAAQMD, SFPUC, EPA and port funds). Staff described a financing package that estimated total capital needs at roughly $6.4 million (staff noted $5.7 million for project costs plus reserves and issuance costs). Under a letter of intent, BAE would construct a 12-megawatt system at Pier 70; the port would fund initial capital and recover costs through a 4'-per-kilowatt-hour equipment charge passed to vessel owners; the SFPUC proposed a $1.5 million rebate contingent on system usage thresholds.
Environmental advocates and BAE representatives spoke in support, citing greenhouse-gas and air-pollutant reductions. Commissioners discussed short-term borrowing from a backlands project to bridge to long-term debt proceeds and asked clarifying questions about repayment timing. The commission voted to approve the shore-power authorization (Resolution 1219), and staff said it would return with appropriation authority if Board of Supervisors action on debt reallocation is favorable.
