SFPUC wastewater CIP updates; staff seeks WIFIA loan interest for $625 million
Summary
Wastewater capital-program director Karen Kubik reported schedule and cost variances on major projects, noted the draft EIR and planning milestones for headworks and biosolids facilities, and said the SFPUC submitted a WIFIA letter of interest for a potential $625 million loan to reduce borrowing costs.
Karen Kubik, Director of Capital Programs for Wastewater, delivered the wastewater enterprise capital-improvement quarterly report on June 13 and highlighted project delays, cost increases and financing efforts.
Kubik said the commission’s red-dot list includes the Southeast power feed and primary switchgear upgrades (delayed two years to align with a separate transmission project), the Marin Street pump-station replacement (all four bids exceeded project estimate) and a $7 million…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat