SFPUC wastewater CIP updates; staff seeks WIFIA loan interest for $625 million
Summary
Wastewater capital-program director Karen Kubik reported schedule and cost variances on major projects, noted the draft EIR and planning milestones for headworks and biosolids facilities, and said the SFPUC submitted a WIFIA letter of interest for a potential $625 million loan to reduce borrowing costs.
Get email alerts on the Wastewater Cip Financing topic
No spam. Unsubscribe anytime.
Karen Kubik, Director of Capital Programs for Wastewater, delivered the wastewater enterprise capital-improvement quarterly report on June 13 and highlighted project delays, cost increases and financing efforts.
Kubik said the commission’s red-dot list includes the Southeast power feed and primary switchgear upgrades (delayed two years to align with a separate transmission project), the Marin Street pump-station replacement (all four bids exceeded project estimate) and a $7 million increase at Griffith Pump Station following a 2016 transformer failure. "We had a transformer that was damaged in mid-2016," Kubik said, describing subsequent replacement and the need for new switchgear and a motor-control center.
On major program milestones, Kubik reported staff is moving biosolids design to 65% and expects construction to start in 2018, that the draft environmental review for headworks was published in May and that the SFPUC plans to put construction-management and trade work out to bid later this year. She said the agency submitted a letter of interest to the EPA for the Water Infrastructure Finance and Innovation Act (WIFIA) seeking a low-interest loan of $625,000,000 to reduce long-term costs for ratepayers.
Kubik reviewed green-infrastructure and local-hire outcomes: 27 active prime contracts (11 professional services, 16 construction), 36% of project hours worked by San Francisco residents (equating to roughly $6.2 million in wages), and continued apprenticeships and entry-level pathways. She said monitoring for green-infrastructure performance will continue through the next wet season, with more definitive modeling results expected about a year after wet-weather monitoring is complete.
Commissioners asked for modeling data to be presented in the context of decision-making and staff said the collection-system plan to be presented in July will include recommended green-infrastructure opportunities and performance data to date.