SFPUC updates SSIP progress; biosolids contract modification and local hire metrics highlighted

San Francisco Public Utilities Commission · March 14, 2017
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

SFPUC staff reported that Phase 1 of the Sewer System Improvement Program includes 70 projects in the $2.9 billion baseline, with 11 projects in construction; staff previewed a roughly $73.5 million modification to the biosolids contract (bringing the total to about $153.5 million) and reported San Francisco residents logged 36% of prime‑contract hours and 72% of apprentice hours on active contracts.

Karen Kubik, director of the Wastewater Capital Program, briefed the commission on SSIP progress and workforce outcomes on March 14. She said the Phase 1 baseline encompasses 70 projects and $2.9 billion in authorized work, with the larger Headworks and Biosolids projects moving toward construction management procurement.

Kubik highlighted several schedule and cost items marked as red‑dot risks, including a 19.9‑month delay to the San Joaquin Pipeline Rehabilitation driven by scope additions, rebids…

Already have an account? Log in

Subscribe to keep reading

Unlock the rest of this article — and every article on Citizen Portal.

  • Unlimited articles
  • AI-powered breakdowns of topics, speakers, decisions, and budgets
  • Instant alerts when your location has a new meeting
  • Follow topics and more locations
  • 1,000 AI Insights / month, plus AI Chat
30-day money-back on paid plans