Citizen Portal
Sign In

Get Full Government Meeting Transcripts, Videos, & Alerts Forever!

Get email alerts on the Budget topic

No spam. Unsubscribe anytime.

Port staff outline $185 million GO bond allocations; Brannan Street Wharf faces $4 million shortfall

Port Commission of the City and County of San Francisco · January 11, 2011
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Deputy Director Elaine Forbes updated the commission on the 2008 general obligation bond allocations and project schedules, including an identified shortfall of about $4 million for the Brannan Street Wharf full build‑out tied to America's Cup viewing requirements.

Deputy Director Elaine Forbes delivered an informational update on the Port's use of the 2008 Clean and Safe Neighborhood Parks General Obligation bond. Forbes said San Francisco voters approved $185 million citywide, of which $33.5 million is allocated to waterfront parks. Staff provided project allocations, noting Pier 43 Bay Trail Link is allocated $7.8 million, the Brannan Street Wharf $2.9 million and Blue Greenway projects $21.6 million. The Pier 43 Bay Trail Link has completed environmental review and entitlements and staff expects to advertise bids and move to an 18‑month construction schedule.

During discussion, commissioners asked about a roughly $4,000,000 shortfall for delivering the Brannan Street Wharf full build‑out. Project manager Steven Meehl explained the base contract can be funded but several additive alternates — a float and gangway (approximately $1.3 million), a shade structure (about $300,000) and an adjacent wharf section tied to Pier 30‑32 — make up the difference. Meehl said the Port can deliver a base project within current funding but that the alternates are needed to meet the desired America's Cup viewing configuration; staff is seeking additional funding and will return with budget recommendations and timing tied to construction and event deadlines.

Forbes said future bond issuances are planned to fund construction readiness and that staff will return with supplemental appropriation requests for upcoming sales. No final appropriation or contract award was taken at this meeting.