SFPUC approves 15‑month schedule extensions for three WISP projects to resolve contractor claims

San Francisco Public Utilities Commission · February 14, 2017
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The San Francisco Public Utilities Commission approved a revised January 2017 WISP schedule that extends three projects by 15 months to allow resolution of contractor change orders and claims; staff said the change does not alter the program budget.

The San Francisco Public Utilities Commission on Feb. 14 approved a revised project schedule for the Water System Improvement Program that extends three projects by 15 months to allow time to resolve contractor change orders and dispute‑resolution matters, staff told the commission.

Dan Wade, Director of Capital Water Projects, asked the commission to approve the January 2017 WISP revision to extend the schedules for New Idria Tunnel, the seismic upgrades to Bayshore/Beta Vision pipelines 3 and 4, and the…

Already have an account? Log in

Subscribe to keep reading

Unlock the rest of this article — and every article on Citizen Portal.

  • Unlimited articles
  • AI-powered breakdowns of topics, speakers, decisions, and budgets
  • Instant alerts when your location has a new meeting
  • Follow topics and more locations
  • 1,000 AI Insights / month, plus AI Chat
30-day money-back on paid plans