Board approves James McHugh design‑build amendment for downtown parking garage amid budget questions
Summary
Trustees approved a resolution advancing the final design and a design‑build amendment with James McHugh Construction for a two‑level downtown parking structure; trustees pressed staff and the contractor on materials, allowance line items and the project’s evolving price while one trustee warned residents should not shoulder lead service line replacement costs.
Get email alerts on the Infrastructure Parking topic
No spam. Unsubscribe anytime.
The East Dundee Board of Trustees voted July 15 to approve a resolution accepting the final design and a design‑build amendment between the Village and James McHugh Construction Company for a two‑level downtown parking structure.
James McHugh representatives reviewed design details and allowances for cornices, corbels and façade options; staff described items added since the original bid that increased cost, including additional stormwater retention required by the county, added landscaping, paving work, and ComEd underground relocation. Staff and the contractor traced the contract price from an initial bid they recalled at about $6,300,000, through a configuration with retail that rose to about $6,900,000, to the final figure presented to the board.
During debate Trustee Sarah (identified in the transcript as a trustee who missed an earlier meeting) pressed the board on fiscal priorities, saying she was reluctant to move forward if residents would later be asked to pay for lead service line replacements. "I don't wanna hear about our residents having to pay a dime for the lead service lines. Not a penny," she said, arguing the village should not force residents to shoulder those costs while also funding the parking project.
Village staff responded that the village can pursue both projects and that sequencing and funding conversations have been ongoing; a staff speaker said the village had the financial capacity to execute both without detrimentally affecting the budget. Trustees requested further decisions on specific materials (cornices/corbels) be returned to the board as final selections are made; staff noted allowances are built into the contract and adjustments could return money to contingency.
The board approved the resolution by roll call. The contract amendment includes design allowances and directs staff and the contractor to finalize selected materials and any alternates before procurement.