Commissioners grant brief completion extension for courthouse addition; laminate delivery issues cited
Summary
After staff reported damaged laminate deliveries and installation challenges, the board extended the DSI construction contract completion date to April 12 to allow finishing work.
Get email alerts on the Construction topic
No spam. Unsubscribe anytime.
County construction staff reported damaged and incorrectly sized laminate panels that delayed parts of the courthouse addition. Rebecca said the contractor encountered material problems and requested extra time to complete installation.
Commissioners considered a short extension to complete finish work and address site punch-list items. The board voted to extend the DSI contract completion date to April 12 to accommodate the remedial work and to allow staff to finalize outstanding changes.
Staff will monitor progress and report back if further extension requests are needed.