Board gets bond construction update as contractors report 70% billed; district approves $35,252 wireless upgrade after E‑Rate
Summary
Teal Construction and contractors told trustees the new high school project is progressing with 70% billed and substantial completion still scheduled for Feb. 2026; the board also approved a district‑wide wireless upgrade (E‑Rate covers 85%), leaving the local cost at $35,252.76 over five years.
Get email alerts on the Construction topic
No spam. Unsubscribe anytime.
Trustees received a detailed progress update on the Bond 2022 projects and voted to upgrade district wireless infrastructure.
Representatives from Teal Construction and the steel contractor provided a site progress report, photos and a schedule. Michael Miller, vice president of steel construction, said the project is “70 completion per billing,” and noted the money authorized to date is $30,340,000 of a total contract value of $39,240,000; substantial completion was described as scheduled in February 2026. Presenters listed outstanding change orders (identified in discussion as numbers 70 and 71) tied to time extensions for steel and dewatering and said the elevator and remaining finish work were in late stages.
Separately, the board approved a district‑wide wireless infrastructure upgrade. Technology staff reported the project total is $235,081.40; because E‑Rate is expected to cover approximately 85 percent, the district’s budgeted share is $35,252.76. The vendor and E‑Rate paperwork require the full project amount on purchase orders, but trustees emphasized the net local outlay will be the smaller, budgeted figure; the motion passed 7–0. Staff said the upgrade covers equipment, installation, and five years of managed services and will replace recurring monitoring costs the district currently pays (~$30,000/year), yielding multi‑year savings.
What this means: Construction staff said work on interior finishes, glazing, and access control integration will accelerate once punch‑list items are closed, and the wireless project will expand reliable Wi‑Fi coverage across all campuses with an E‑Rate subsidy reducing the local budget impact.