The CIP committee told the selectboard an updated quote raised library AC/air-handler work from about $90,000 to roughly $250,000 and recommended designating the library cistern replacement (approx. $46,000) as an emergency with funds allocated from library reserves and CRF.
Get email alerts on the Capital Projects topic
No spam. Unsubscribe anytime.
Members of Bow's Capital Improvements Program (CIP) committee reported revised cost estimates and several funding recommendations to the selectboard on Sept. 23.
The committee recommended holding the school capital contribution at $1,000,000 and keeping a $500,000 allocation for community-center options. A late updated quote significantly increased the anticipated cost for library AC and air-handler work from about $90,000 to an estimated $250,000; the committee asked the selectboard and budget committee to review options.
CIP recommended classifying the library cistern replacement as an emergency. The committee suggested using about $29,000 from the library emergency fund and $17,000 from the library capital reserve fund — a combined estimated $46,000 — and proposed resuming a modest annual contribution to the library emergency fund (proposed $2,500/year) to ensure future readiness.
Committee members discussed moving a one-ton truck line item from municipal buildings to Parks & Recreation on the basis of primary plowing use, and suggested selling the Bobog Meeting House to reduce long-term taxpayer burden. The committee reported a modest net reduction in total recommended contributions (about $17,500) excluding the library AC increase.
Ending: The selectboard thanked CIP for early submission and asked staff and the budget committee to review the revised library project costs ahead of budget sessions.