Bettendorf board approves Russell Construction as construction manager‑at‑risk for middle‑school renovation

Bettendorf Comm School District Board of Directors · August 22, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The Bettendorf Comm School District board approved Russell Construction as the construction manager‑at‑risk for the Bettendorf Middle School renovation after the administration described a competitive RFQ and interview process; the transcript records the motion as 'Motion carried 5 0 1.'

The Bettendorf Comm School District board voted to approve Russell Construction as the district’s construction manager‑at‑risk for the planned Bettendorf Middle School renovation, the district recommended during Monday’s meeting.

The superintendent told the board the district issued a request for qualifications in July and received seven submissions. After interviews and reference checks, administration said it recommended Russell Construction as "the partner that works with Bray and the district" on the four‑year renovation project. "We are recommending Russell Construction," the superintendent said during the discussion.

The administration told board members the procurement prioritized qualifications and experience with occupied K‑12 renovations rather than lowest fee alone. The superintendent said sealed fee proposals were submitted during the interview process and reviewed only after the district completed qualitative rankings; in the top firms the fee variance was "no more than about $500,000." He also said the project ceiling was "33 and a half million dollars," a limit respondents knew when they submitted qualifications.

Design‑team staff and the superintendent described reference checks and preconstruction services as key criteria. A Bray representative and other staff said Russell had demonstrated phasing and preconstruction planning they valued; another speaker confirmed North Scott had previously worked with Russell and provided mixed but ultimately acceptable feedback about personnel matches on past projects.

The board moved, seconded and took a roll‑call vote on the recommendation; the transcript records the result as "Motion carried 5 0 1." Administration said the selected firm will help sequence the work and begin preconstruction planning after board approval.

Funding specifics, contract amounts and the effective date of any agreement were not detailed in the transcript. The administration said further scoping and preconstruction work will happen next week to refine sequencing and cost mitigation steps.