Council approves change orders and budget amendments for Silver Creek pump station project

Morganton City Council · September 10, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Council approved two change orders—$12,143.02 for a stairway and $77,317.77 to replace an automatic transfer switch—and two budget amendments totaling $280,161 to move contingency funds into construction for the Silver Creek Sewer Pump Station improvements project, increasing the construction portion toward a roughly $8 million total project estimate.

City staff presented three related agenda items for the Silver Creek Sewer Pump Station Improvements project: two construction change orders and two budget amendments to move contingency funds to construction.

Sally Sandy explained change order #2 adds a metal stairway to meet code at a cost of $12,143.02 and change order #3 replaces an automatic transfer switch destroyed by Hurricane Helene for $77,317.77. "That money will be coming out of contingency for this project," she said.

Council approved both change orders by voice vote. Sandy said the construction portion of the project is approaching $6.5 million and the total project including engineering and other costs is "almost an $8,000,000 project now."

To fund the change orders, staff presented and the council approved two budget amendments: $89,461 to transfer contingency to construction and $190,700 to increase the project fund for additional construction time. The amendments were approved by voice vote.