Select Board approves DuBois & King studies and 60% design for South TIF water extension
Summary
The board approved a $27,000 amendment to DuBois & King for booster‑station vs. storage‑tank modeling and authorized a $216,002.96 60% design contract for the South TIF water extension, funded from the TIF district.
Get email alerts on the Engineering Contracts topic
No spam. Unsubscribe anytime.
At the May 27 meeting the board approved two engineering actions to refine the town’s water‑system planning. First, the board authorized an amendment (Amendment #3) to the existing DuBois & King contract for a lump‑sum $27,000 scope to model a conceptual booster pump station option, produce conceptual design and an opinion of cost and compare that to storage‑tank alternatives. Supporters said the additional modeling is needed to compare lifecycle costs, energy and maintenance tradeoffs.
Second, the board approved entering a contract with DuBois & King for 60% design work on the South TIF water extension in the lump sum of $216,002.96; staff said TIF district funds are available to cover the work. The 60% design includes topo/base map updates, alignment, geotechnical work and the typical suite of services to move toward final design and procurement.
During discussion Tom O’Donovan (Open Spaces/Drinking Water Committee) urged that all siting and design options remain under consideration and cautioned about long‑term energy and maintenance differences between booster pumps and storage tanks. The board voted in favor of both actions.
Next steps: DuBois & King to proceed with the modeling and to deliver the 60% design deliverables; staff will return estimates and comparative analyses to the board for any later construction or procurement votes.