Get Full Government Meeting Transcripts, Videos, & Alerts Forever!
Get email alerts on the Drainage Repairs topic
No spam. Unsubscribe anytime.
Benton County delays final acceptance of CD 9 and CD 14 repairs amid notice and inspection concerns
Summary
At a lengthy Ditch Authority hearing, county attorneys found defective notice for the CD 9 contract‑acceptance hearing and commissioners set a new hearing for March 4 at 6 p.m.; the board continued the CD 14 acceptance to June 3 to allow additional inspection and outreach after landowners raised questions about assessments and incomplete contractor work.
Get email alerts on the Drainage Repairs topic
No spam. Unsubscribe anytime.
The Benton County Ditch Authority paused final acceptance of two drainage repairs after residents raised concerns about who received required legal notices and whether all contracted work was completed.
At the February hearing, county counsel Hannah Shackle Jensen told the authority that the statutorily required notice for the CD 9 contract‑acceptance hearing had not been mailed to all benefited landowners, including owners on interconnected systems (CD 12 and CD 14). "The board should direct staff to send notice to the landowners who were not sent notice for CD 9 and set a date and time for that contract acceptance hearing," Hannah said, recommending a limited re‑notice only to those omitted.
That recommendation prompted a separate motion and vote. The board set the CD 9 contract‑acceptance hearing for March 4 at 6:00 p.m. and directed staff to mail notice to benefited landowners on CD 9, CD 12 and CD 14.
The meeting then focused on County Ditch 14, where Houston Engineering summarized the multi‑year repair process — record reestablishment, redetermination of benefits, repair report, regulatory coordination and construction bids. Engineer Joe (Houston Engineering) said the repair report estimated CD 14 costs at about $979,000 (with a construction estimate near $520,000) but the awarded construction contracts ultimately came in lower. "We measured channel sediment, replaced culverts and purchased wetland credits where the repair caused impacts," Joe said, describing the work completed and the post‑construction as‑built surveys used to verify depths and culvert elevations.
Multiple landowners then described what they said were unresolved issues: woody vegetation left within easements, trees not removed where required by the bid, and confusion about the redetermination of benefits and resulting assessment calculations. One resident, Mark Ratko, praised the dredging overall but asked why some areas still show standing woody vegetation: "How is it fair to landowners that we're assessed for work that wasn't completed?" he asked.
County staff and the engineer described the contract administration process: inspectors document quantities, contractors invoice by measured units and final payments follow verification. The authority agreed it needed to verify specific contested quantities and inspect areas alleged to be incomplete before final acceptance and assessment certification.
Faced with the volume of public questions and several contested locations that need field verification, the board voted to continue the CD 14 contract‑acceptance hearing and assessment adoption. The continuation was scheduled for June 3 at 6:00 p.m. The board directed staff and the county engineer to re‑verify inspection quantities, document any contractor deficiencies, and coordinate outreach with viewers and H2O reviewers so landowners can review their redetermination of benefits packets.
What happens next: staff will mail the required notices for the March 4 CD 9 hearing, and the June 3 continuation for CD 14 will include follow‑up testimony and the authority’s findings on any outstanding work or quantity adjustments. The board also reminded landowners that, if the repair order and redetermination become final without timely appeal, the statutory deadlines for challenging those determinations have passed; counsel said staff will nonetheless pursue remedy by renotification where notice was defective.
The Ditch Authority meeting closed after the board set the two hearing dates and instructed staff to gather verification materials and mailing lists.

