Get Full Government Meeting Transcripts, Videos, & Alerts Forever!
Get email alerts on the Transportation Projects topic
No spam. Unsubscribe anytime.
Benton County rejects Rice pedestrian crossing bids, moves forward with Mayhew Lake roundabout award contingent on DBE review
Summary
County engineers recommended rejecting bids for a Rice railroad pedestrian crossing after the low bid more than doubled the estimate; the board also approved awarding a contract for the Mayhew Lake Road roundabout to Knife River (2.7% over estimate), contingent on MnDOT DBE compliance and federal funding conditions.
Get email alerts on the Transportation Projects topic
No spam. Unsubscribe anytime.
BENTON COUNTY — Benton County engineers told the board Thursday they would reject bids for a Rice railroad pedestrian crossing after bids came in substantially over the engineer's estimate, and the board approved moving forward on a Mayhew Lake Road roundabout after receiving a higher-than-estimated but acceptable low bid.
On the Rice pedestrian crossing (Project S P005-090-005), county staff reported three responsible bids were received and the low bid, from Tyczak Concrete LLC, was $213,321.86 against an engineer estimate just above $103,000. The Rice City Council had previously voted not to move forward; county staff recommended rejecting all bids, re-advertising in the fall, and considering a winter bid opening to reduce pricing pressures. Commissioners voted to reject and re-advertise.
The board then considered bids for a roundabout at Mayhew Lake Road (Project S P005-070-014). Several bids were received; Knife River, North Central Division, submitted the lowest responsible bid at about 2.7% above the engineer's estimate. The county's portion of the project was estimated at $2,605,440.03; the project carries federal HSIP funding of $1,940,000 and a carbon-reduction grant of $440,000. County Engineer Chris said the remaining local share would likely be covered by local-option sales tax and other local funds. He emphasized the award must be contingent on MnDOT Office of Civil Rights review for a 7.5% disadvantaged-business-enterprise (DBE) participation goal. Commissioners voted to accept the low bid and authorized the chair to sign the award contingent on the DBE review.
The Rice crossing will be re-bid with adjustments to the bid structure and timeline, and the Mayhew Lake roundabout will proceed to contracting pending state review of DBE compliance.

