Board accepts certificates of occupancy, approves final GMP for Hilltop School for the Arts

Agua Fria Union High School District Governing Board · July 11, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Contractors and district staff marked the Hilltop School for the Arts project milestone: three buildings received certificates of occupancy and the board approved Guaranteed Maximum Price No. 3, which staff described as the final GMP covering the remaining project costs.

Contractors with Chase Building Team presented plaques and noted a milestone in the Hilltop School for the Arts construction: three main buildings received certificates of occupancy on July 3, and Chase representatives thanked the board and district staff for the partnership.

"On behalf of Chase Building Team, we just wanna say thank you for the opportunity... July 3 was exactly one year since we started moving dirt on this project. And on July 3 year, we got our certificate of occupancy for, 3 buildings," Connor Lewis said during public comment as he introduced colleagues and presented plaques to the governing board.

Following the presentation, a project representative described Guaranteed Maximum Price No. 3 (GMP No. 3) for the Hilltop School for the Arts and characterized it as the third and final GMP intended to cover the remainder of project costs and some contingency allowances. "This is our third and final GMP that covers the entire cost of the school, as well as a couple things just to cover our bases in case there are any extras on the project," the presenter said.

The governing board approved the GMP as presented. The transcript records the approval language and board members' oral assent; a full roll-call vote with named tallies was not recorded in the meeting transcript.

Why it matters: Certificates of occupancy mark when buildings meet code and can be put to their intended use. Approving a final GMP determines the construction cost ceiling and clears the way for project closeout and occupancy planning.

What's next: with certificates of occupancy and GMP approval complete, the district and contractors will move to final occupancy logistics and any remaining punch-list work.