Rockport-Fulton ISD: High school additions 66% complete; full project now set for February 2026
Summary
At its June 19 meeting the Rockport-Fulton ISD board heard a Bond 2022 construction update: contractors reported RFHS additions are 66% (billing) complete, the district authorized $25.7 million for the project, and full substantial completion moved to Feb. 2026 while classroom areas may be ready for occupancy as early as October 2025.
The Rockport-Fulton Independent School District received a Bond 2022 project update at its June 19 board meeting in which construction contractors reported progress and revised timelines for two campus projects.
A Teal Construction representative told trustees the Rockport-Fulton High School additions and renovations are about 66% complete on a billing basis and that the district has authorized $25,700,000 for the project. The contractor said paperwork recognizing delay notices pushed the overall substantial-completion date for the full project to February 2026, while an early-occupancy target for the classroom wing and adjacent fine-arts spaces is targeted for early October 2025 to allow…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat