Wagner council approves contractor payments, vows to hold retainage until pickleball punch list fixed
Summary
The City of Wagner approved several contractor pay applications Sept. 2, including work by Glover & Associates, Eagle Eye Construction and Darris Contractors, while council raised concerns about site cleanup and fencing at the new Lincoln Park pickleball courts and said retainage will be held until a final inspection.
Get email alerts on the Capital Projects topic
No spam. Unsubscribe anytime.
The Wagner City Council on Sept. 2 approved multiple contractor payments for ongoing park and utility projects but flagged outstanding work at Lincoln Park that councilmembers said must be finished before full final payments are released.
Council voted to pay contractor pay application No. 4 to Glover & Associates for $94,790.45 after the project lead said Glover had agreed to address outstanding punch‑list items and had started corrective work. Project staff told the council the contractor provided a schedule and expected to complete work by the next council meeting, and members agreed to hold retained funds until a final inspection confirms completion.
The council also approved pay application No. 3 to Eagle Eye Construction for $19,488.29 for the new Lincoln Park pickleball court, but members pressed for cleanup and fence repairs before recommending release of retained funds. Project lead (speaker 7) said courts were painted and nets were due to be installed and recommended payment for the work completed; other council members described visible problems around the site. "It looks real good. I mean, it's horrible," one council member (speaker 16) said when describing the surrounding fencing and unfinished bathrooms, underscoring the council's concern that site conditions remained incomplete.
Council discussed options for replacing damaged fencing, noting the contractor's scope did not include fence work and that the council had budgeted fence replacement for a different park. Project staff said they would identify cleanup and fencing items during the final inspection and that retainage would be withheld until those items were corrected.
On the utility side, council approved pay application No. 2 from Darris Contractors LLC for $12,415.52 for work on the wastewater treatment plant headworks (WAG‑23‑02), following the same recommendation from Infrastructure Solutions Group LLC.
What happens next: council members said inspectors will perform a final site walk to verify the fence, site cleanup and restroom work before recommending release of retainage and final payments.