Board reviews schematic designs, PennDOT traffic scope and geotech work for Green Village school site
Summary
Dr. Long and project partners updated the board on schematic designs for a proposed intermediate/elementary school at Green Village, described a three‑story option to conserve site footprint, reported PennDOT’s traffic scoping requirements and HRG geotechnical testing, and outlined a construction target of May 2029.
Get email alerts on the Facilities Design topic
No spam. Unsubscribe anytime.
Dr. Long and Mr. Varner presented a facilities update focused on designs for a new intermediate/elementary school at the Green Village property. They emphasized the schematic is a draft and described a three‑story option that would reduce building footprint and shorten travel distances within the school (SEG 270–289; SEG 295–305).
Staff reported PennDOT engagement: a Traffic Impact Study (TIS) scoping application was submitted Aug. 16 with a Sept. 10 scoping meeting, and PennDOT required study of 13 intersections plus the I‑81 northbound exit ramp. The project was recommended for a PennDOT pilot program intended to expedite highway occupancy permits (HOPs), but speakers cautioned expected time savings are still unclear (SEG 250–266; SEG 257–265).
HRG, the district’s civil engineering partner, began surveying and geotechnical field exploration in August and started test pits Sept. 17. DEP required a set of test sites; after DEP review the team obtained approval for a less invasive borehole testing method to preserve athletic fields, with drilling scheduled for roughly 3–4 days (SEG 391–417).
Design team notes included site option tradeoffs: some potential building locations were eliminated because of stormwater runoff, utilities, and access. The presenters identified two promising site orientations ("Northeast" and "park side") and said they expect to narrow options and return next month with updated drawings and civil engineering input (SEG 372–389; SEG 456–467).
Timeline: the schematic phase for Crabtree is expected to complete in October and RLPS in November, with separate bid packages planned and construction aimed to finish by May 2029 to align with student occupancy goals (SEG 418–432).
Next steps: further site refinement with civil engineers, a borough coordination meeting, and continued schematic development prior to bidding. Board members asked clarifying questions but did not block progression of the schematic design process (SEG 468–472).