Board approves revised facility plan to pursue renovation, not replacement, for middle school
Summary
Bath County’s school board approved a revised District Facility Plan asking KDE to record a renovation (not a new-build) for the middle school; staff explained KDE caps new-school funding at 80% and provided a $10 million example figure used for recordkeeping and BG-1 scoping.
Get email alerts on the Facility Plan topic
No spam. Unsubscribe anytime.
The Bath County Board of Education voted Feb. 17 to approve an updated District Facility Plan (DFP) that requests the Kentucky Department of Education (KDE) reflect a renovation approach for the district’s middle school rather than a new-build.
District staff explained the DFP must retain historical items (for example, the prior intent for a new middle school is shown crossed out) for KDE recordkeeping. Staff emphasized that KDE’s cost figures function as a budgeting reference: KDE applies an 80% cap on eligible renovation funding compared with KDE’s estimate for a new school. As an example, staff said KDE would cap renovation budgeting at $20 million if KDE’s new-school estimate were $25 million.
Staff also pointed to a line-item section (labeled priority 1c) that lists building sections qualifying by age for replacement and shows a KDE-funded example figure of $10,000,000 for anticipated work on the oldest sections. Staff characterized that $10 million as KDE’s replacement estimate and said the board ultimately chooses which items to place on a BG-1 application when it scopes an actual project.
Board members discussed bonding capacity and grant funds, noting the district had about $7.1 million in grant funding that must be factored into project scoping. Members cautioned that allocating too much bonding to a single renovation could exhaust local bonding capacity and leave little funding for other district needs.
Eric moved to approve the revised DFP and Carla seconded; the motion carried by voice vote. Staff said the revised DFP will be sent to KDE to request the change in plan status so the district can proceed with BG-1 scoping and grant planning.