Albany High construction near completion but contractors and board flag punch-list defects

Albany City School District Board of Education · September 12, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Turner Construction reported Phase 4 occupancy and substantial punch-list progress at Albany High but disclosed water infiltration at certain edge-band lap joints and subbase deficiencies on the Loop Road; the board urged a firm stance on remediation and legal counsel involvement for warranty and contractor accountability.

Turner Construction and project contractors told the Albany City School District Board the Phase 4 portion of the new Albany High School is occupied and largely nearing closeout, but several remaining punch-list items and construction deficiencies require remediation.

Bob Grande of Turner Construction said interior punch-list work and site items (connector addition, parking and crosswalks, ADA strips and plantings) are ongoing. Grande said theatrical lighting and rigging for the Level 1 theater are long-lead items…

Already have an account? Log in

Subscribe to keep reading

Unlock the rest of this article — and every article on Citizen Portal.

  • Unlimited articles
  • AI-powered breakdowns of topics, speakers, decisions, and budgets
  • Instant alerts when your location has a new meeting
  • Follow topics and more locations
  • 1,000 AI Insights / month, plus AI Chat
30-day money-back on paid plans