District updates Percy Julian High and South Lawn Middle construction; South Lawn gym change order explained
Summary
Volker reported Percy Julian High is ~5% complete with a December 2027 target and early foundation work beginning; South Lawn Middle is ~86% complete pending approval of Change Order No. 1 (utility revisions, termite treatment, MDF closet) and remains reported under budget by about $1.6 million.
Volker project staff updated the Montgomery County Board of Education on major capital projects, including early work at Percy Julian High and finishing tasks at South Lawn Middle.
Percy Julian High: Volker’s Miss Penn said the Percy Julian project is tracking about 5% complete with a target substantial-completion date of December 2027. The contractor is preparing building pads and beginning foundation excavation; soil grading and pond work…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat