Get Full Government Meeting Transcripts, Videos, & Alerts Forever!
Get email alerts on the Capital Projects topic
No spam. Unsubscribe anytime.
District updates Percy Julian High and South Lawn Middle construction; South Lawn gym change order explained
Summary
Volker reported Percy Julian High is ~5% complete with a December 2027 target and early foundation work beginning; South Lawn Middle is ~86% complete pending approval of Change Order No. 1 (utility revisions, termite treatment, MDF closet) and remains reported under budget by about $1.6 million.
Get email alerts on the Capital Projects topic
No spam. Unsubscribe anytime.
Volker project staff updated the Montgomery County Board of Education on major capital projects, including early work at Percy Julian High and finishing tasks at South Lawn Middle.
Percy Julian High: Volker’s Miss Penn said the Percy Julian project is tracking about 5% complete with a target substantial-completion date of December 2027. The contractor is preparing building pads and beginning foundation excavation; soil grading and pond work are underway. Penn said building-pad certification for sections A and C was scheduled for Aug. 15 and that vertical construction should become visible later this year.
South Lawn Middle: Penn reported South Lawn Middle at approximately 86% complete and said the change-order presentation (Change Order No. 1) covers several no-cost schedule adjustments related to water, sewer and fire-line revisions plus cost items for termite treatment, structural beam revisions and the addition of an MDF closet to accommodate IT infrastructure. Volker stated the project remains approximately $1.6 million under the originally allotted budget.
Minority contracting and participation: Penn reviewed MBE/DBE participation, saying professional-services participation rose (45% in that category) while construction contracting participation remains low; she said Volker can recommend vetted subcontractors but the general contractor selects subs under state bid laws. Board members pressed for ongoing efforts to increase minority-subcontractor participation.
What’s next: Penn said site activities will move to foundation work and that the district will follow up on minority-participation strategies and schedule confirmations. The board thanked the Volker team for the update; no final board action on the Percy Julian schedule was taken during the session.

