Capital projects update: oversight committee feedback and timeline for new Issaquah high school

Issaquah School District Board of Directors · June 27, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Director of capital projects Tom Mullins updated the board on 2018 and 2022 levy project statuses, oversight-committee recommendations to improve public information, and said the new high school project is under revision with city staff; the transcript records an erroneous construction date that requires verification.

Tom Mullins, the district's director of capital projects, briefed the board on the status of levy-funded work and the new high school during the meeting.

Mullins said the 2018 levy has 28 projects complete, seven in substantial completion, seven still in process and two future projects. He reported the 2022 critical-repairs levy has one project complete, one substantially complete, 12 in process and one future project. The Capital Projects Oversight Committee met in mid-June; 17 of 26 members attended and provided feedback requesting clearer public materials on project scope, budgets and change orders.

Committee members asked the district to expand the "project pagers" (succinct status sheets), provide plain-language explanations of change orders, and add context when schedules deviate from original timelines. Mullins said the district is working to implement those usability improvements on the capital projects website and scheduled the next oversight committee meeting for Sept. 16.

Mullins also provided an update on the new high school, saying staff continue to revise plans and meet with city staff about submittal and review timelines. He cited an expected opening date of Aug. 27 but the transcript records a target construction date of "03/01/1926," which is a clear transcription error; the board acknowledged the update and discussed outreach and discoverability for residents who may not visit the district website.

Board members raised questions about whether the oversight committee members had located materials on the website and how to improve "push" and "pull" communications; Mullins said staff will follow up with communications to members who missed meetings and consider ways to feature key topics for discoverability.

No formal action was taken on capital projects at the meeting; Mullins said the district will continue to update the website and incorporate committee recommendations.