Council approves Tustin Sports Park turf contract and directs staff to track problematic bidders
Summary
After debate over an original low bidder who withdrew, the council awarded the Tustin Sports Park Field 3 turf contract and directed staff to develop a bidder‑tracking process; City Attorney said tracking is permissible but disqualification requires a separate process. Vote was 4-1.
Get email alerts on the Procurement Contracts topic
No spam. Unsubscribe anytime.
Tustin — The Tustin City Council voted to award the construction contract for the Tustin Sports Park turf renovation (Field Number 3) while adopting a council direction to create a formal tracking process for contractors that have had performance or responsibility concerns.
Council Member Fink told colleagues he supported awarding the contract to the alternative (second) bidder but was concerned that the originally successful bidder later backed out and presented a substantially higher price, arguing that the city should hold contractors accountable and consider a tracking list for bidders with repeated problems. Fink said a bid is a fixed-price offer and asked for a process to record problematic bidders over a five-year history.
Councilman McGeoger and others noted legal limits. The City Attorney advised that the city can track contractor issues and bring evidence to the council, but formal disqualification (a finding of non-responsibility) must follow the public-procurement procedures in the Public Contract Code.
Council considered two motions: an amended motion from Council Member Fink to add direction for staff to track bidders, and a motion to accept staff’s procurement recommendation. The motion to accept the staff recommendation passed with a 4-1 tally; Council Member Fink cast the lone dissent. The council also directed staff to develop a non‑disqualification tracking mechanism so problem bidders can be documented for future council consideration.
Next steps: staff will finalize the contract award to the recommended bidder and begin implementing the tracking process described to the council; any formal debarment or finding of non-responsibility would require a separate administrative process under the Public Contract Code.