Planning staff proposes $40,000 base plus $100/MW rezoning fee for EU‑2 nuclear zoning; supervisors back higher rate
Summary
County planning staff recommended a $40,000 base fee plus $75–$100 per megawatt for rezoning to an EU‑2 exclusive‑use nuclear zone; supervisors expressed support for the higher $100/MW figure and staff said a resolution to amend the zoning fee schedule will be placed on next week's consent agenda.
Get email alerts on the Zoning Fee Eu2 topic
No spam. Unsubscribe anytime.
Charlie Nichols, planning and development, presented a proposal to set an application fee for rezoning land to an EU‑2 exclusive‑use zoning district for nuclear power generation. Nichols said the county’s best comparator is the large renewable energy rezoning fee used for the Dwayne Arnold solar project and recommended a different formula for nuclear due to complexity and expected review costs.
Nichols proposed a base fee of $40,000 plus a per‑nameplate‑megawatt charge in the $75–$100/MW range to pay for public meeting facility rentals, audiovisual streaming, third‑party technical reviews, legal review, training and other costs that may arise during a multiyear permitting process. Using the Duane Arnold Energy Center as an example (640 MW nameplate), Nichols presented hypothetical totals: $88,000 at $75/MW and $104,000 at $100/MW.
Supervisors voiced support for the higher rate, citing the multi‑year timeline and the need to cover staffing, consulting and meeting costs. Nichols said he would draft a resolution amending the county’s zoning fee schedule to set the EU‑2 rezoning fee at a $40,000 base plus $100 per megawatt and place that resolution on next week’s consent agenda for formal adoption.