Council awards Cracero Park play-area contract and accepts $170,900 water‑conservation grant

Mission Viejo City Council · February 25, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The council awarded a construction contract for the Cracero Park play-area rehabilitation (not to exceed $916,113) and adopted a budget amendment to accept a $170,899.99 Metropolitan Water District water‑conservation grant to support the project.

The Mission Viejo City Council voted unanimously to award a construction contract for the Cracero Park play‑area rehabilitation and to amend the project budget with a water‑conservation grant from the Metropolitan Water District.

Staff recommended awarding the contract to Micron (MyCon) Construction Inc. for an amount not to exceed $916,113, including the base bid and one alternate that adds a concrete walkway with seating to improve park circulation. Staff reported 14 plan sets were sold, 12 contractors attended the mandatory pre‑bid meeting, and four bids were received; Micron was the lowest responsive bidder and has completed similar park projects for the city.

Council Member Kelly publicly thanked staff members Matt Lockwood and Rosa Vasquez for securing the $170,899.99 grant and moved approval of the contract and budget amendment. The motion was seconded and carried in a verbal unanimous vote.

Staff said construction is anticipated to begin in March–April 2025 with completion targeted for late 2025.