Madison County approves five-year secondary roads construction program as engineer warns of tight funding

Madison County Board of Supervisors · April 16, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

After a detailed presentation from the county engineer, the Madison County Board of Supervisors approved the Secondary Roads five-year construction program and parallel secondary road budget, with officials noting limited local funds and borrowing limits for Farm-to-Market revenues.

Madison County approved its Secondary Roads five-year construction program and the accompanying secondary road budget after a detailed briefing by the county’s road engineer.

The presentation, delivered by Mike Fletcher, outlined the program’s purpose as a planning tool for large projects and daily operations, and linked the county’s plan to Iowa Department of Transportation processes. Fletcher said the county manages 916 miles of highway, of which 744 are gravel and about 114 miles are paved. He also warned of constrained local funding: "Madison County's current farm to market balance is negative 300,000.0," he said, and noted the county receives about $1,000,000 a year in Farm-to-Market revenues.

Fletcher walked the board through funding sources available for large projects — Farm-to-Market, STBG (surface transportation), Highway Bridge Program (HBP)/SWAP, HSIP/TSIP safety funds, county and city bridge funds, congressional community project funds and local match dollars — and explained eligibility and match requirements. He said the county receives about $930,000 a year in HPP/SWAP funds and that many projects depend on combining federal aids and local matches.

Fletcher also provided cost benchmarks used for planning: a 75–125-foot bridge roughly $650,000, larger bridges up to about $1.8 million depending on span, resurfacing rehabilitation roughly $450,000 per mile and full-depth new paving near $1,000,000 per mile. He highlighted inventory and condition issues, saying Madison County has 208 bridges longer than 20 feet and that many structures approach or exceed 70 years old.

Board members moved and seconded approval of the five-year construction program and the secondary road budget following Fletcher’s presentation; the motion carried on a voice vote. The engineer and board members emphasized that Year 1 funding must be identified for projects to proceed and that projects entering the state STIP become obligated, making later removal difficult without replacing them with equivalently funded projects.

The board directed staff to post the program and associated interactive maps and to follow statutory submission procedures to the Iowa DOT. Fletcher told the board he would post the DOT five-year construction maps and related materials on the county website for public review.

The board’s approval does not guarantee immediate construction; members noted many projects in years 2–5 are planning placeholders dependent on future funding and competitive grants. The county also discussed using day-labor crews for smaller culvert and minor repairs while larger bridge and paving projects await matching funds.