Council Approves $3.7M SB1 Pavement Projects Targeting North and West Neighborhoods
Summary
The council adopted a recommended SB1 (gas tax) project list for FY25/26 totaling about $3.7 million focused on North and West side overlays, prioritizing equitable distribution and coordination with water main replacements.
Get email alerts on the Roads Sb1 topic
No spam. Unsubscribe anytime.
Fullerton — City engineers presented a recommended SB1 pavement program for FY25/26 at the council’s April 1 meeting and the council adopted the program that directs approximately $3.7 million toward two priority paving projects.
City Engineer Dave Grantham said the city expects roughly $3.7 million in SB1 (gas tax) funding next year and recommended an arterial/local split that funds a north side overlay ($2.5M) and a west side overlay ($1.2M). Grantham explained staff prioritized areas where recent water main work has completed subgrade investigations and where a two‑inch grind and overlay would be economical.
Council members discussed coordination with water main projects and with OCTA for potential funding on corridor projects such as Acacia Avenue, and asked staff to improve notification to residents about sequencing of utility repairs and paving. Grantham said Commonwealth work and other projects will affect adjacent streets and that some high‑need local streets require reconstruction rather than overlays.
The council adopted the SB1 project list by roll call vote.
Next steps: Staff will finalize project designs, coordinate with water and utility schedules, pursue grant opportunities and begin outreach to affected neighborhoods before construction.