Phase 1 of Thelma Avenue Community Gardens received a low bid of $836,415 (Green Giant Landscaping) plus two additive bids (privacy screening $30,000; public art $70,000). With available funds of $635,000 and a 20% contingency proposed, staff reported a funding shortfall of $404,135 and council discussed excluding lighting and phasing art to close the gap.
Get email alerts on the Parks And Recreation topic
No spam. Unsubscribe anytime.
Thelma Avenue Community Gardens Phase 1 drew three bids; staff recommended awarding the base bid and a privacy‑screening additive but noted a budget shortfall that could exceed $400,000 if a 20% contingency is included.
Norm Ray said the low bidder was Green Giant Landscaping of La Habra with a base bid of $836,415. Additive Bid A (privacy screening) totaled $30,000 and a public art feature was bid at $70,000 as an additive item. Staff said available funds total about $635,000; with the recommended base plus privacy screening ($866,415) and a 20% contingency, the project would exceed $1 million and create a $404,135 funding gap.
Public commenter Nancy, a long‑time resident, urged completion and asked the city to maintain the gardens after construction. Council members praised the community’s engagement — the gardens are fully occupied — and debated ways to reduce cost: options included postponing or removing lighting (staff said Edison limits occupancy to dawn‑to‑dusk and that the low bidder’s electrical line item totaling about $144,000 includes both gates and lighting), making the privacy screening in smaller segments to ease graffiti abatement, deferring the $70,000 public‑art element to a later phase, and trimming concrete paving at the gates (bid item $56,400).
Staff noted it could reconfigure the additive scope, request a revised bid that excludes lighting or reprice items, or reject bids and rebid in a later fiscal year. Council indicated support for moving forward with base work and privacy screening while excluding or postponing lighting and said staff should return with a budget‑amendment proposal; staff said the undesignated general fund could be a potential funding source if council chooses to proceed this fiscal year.
No final contract award was executed at the meeting; council directed staff to return with a detailed budget amendment and reduced contingency approach for consideration.