Commissioners approve courthouse change orders, final sewer contract adjustment and direct staff to pursue EMS property exchange with Pinehurst
Summary
Board approved two courthouse change orders increasing the contract sum by $211,414, accepted a $288,843.05 underrun on the VAST phase 2 sewer contract, and directed staff to pursue a property exchange with the Village of Pinehurst to secure a 0.92‑acre site for a new EMS base.
Capital Projects Manager Rich Smith requested approval of two change orders (No. 11 for $136,427 and No. 12 for $74,987) for the new courthouse and renovation project with New Atlantic Contracting; he said those items raise the contract sum to $42,785,318 (a net increase of $211,414) and that the additional funds are available in the capital project fund (fund 432). Smith described technical items including extra soil nailing needed after auger refusals and an HVAC booster…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat