Council reviews small contingency payouts, roundabout utility test pits and paving change order
Summary
City staff told the council $5,400 is needed to correct plats and about $5,492 is expected for roundabout utility test pits; staff said ARC funding likely covers those costs but the city would reallocate sewer funds if ARC won’t cover them. A $15,000–$18,000 paving change order was proposed with Glendenning ad-alternate dropped to stay within budget.
Speaker 1, an unidentified speaker, told the council that $5,400 is required to finalize plat corrections requested by homeowners and that the money is already obligated to the project and held in contingency; Speaker 1 said invoices would require council approval before payment.
On the roundabout project, Speaker 1 said unforeseen utility conflicts required additional test pits by the design engineer, Brutus Engineering, to locate Verizon,…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat