Council reviews small contingency payouts, roundabout utility test pits and paving change order
Summary
City staff told the council $5,400 is needed to correct plats and about $5,492 is expected for roundabout utility test pits; staff said ARC funding likely covers those costs but the city would reallocate sewer funds if ARC won’t cover them. A $15,000–$18,000 paving change order was proposed with Glendenning ad-alternate dropped to stay within budget.
Get email alerts on the Infrastructure Funding topic
No spam. Unsubscribe anytime.
Speaker 1, an unidentified speaker, told the council that $5,400 is required to finalize plat corrections requested by homeowners and that the money is already obligated to the project and held in contingency; Speaker 1 said invoices would require council approval before payment.
On the roundabout project, Speaker 1 said unforeseen utility conflicts required additional test pits by the design engineer, Brutus Engineering, to locate Verizon, Comcast, Columbia Gas and FirstEnergy lines. Speaker 1 gave a working figure — ultimately discussed as $5,492 — for necessary test-fitting work and said the city was “fairly certain” the cost should be eligible under ARC funding but was awaiting formal confirmation. If ARC denies eligibility, Speaker 1 said the city would reallocate funds from other sewer-related budgets.
Speaker 1 also described a proposed small contract change for paving: a rough estimate of $15,000–$18,000 to extend First Street and perform remediation paving in Pritchard Farms after recent heavy rains and manhole relocations. To avoid exceeding the paving budget, staff proposed dropping the Glendenning ad-alternate and reallocating funds to cover First Street and Pritchard Farms work; Speaker 2 confirmed the Glendening projects were last on the list and the change would not exceed the overall paving appropriation.
Council members asked clarifying questions about the utility locations and the city’s contingency approach; Speaker 3 observed the additional amounts represented a small portion of the overall project. No formal motion or roll-call vote on specific contingency disbursements was recorded during the discussion; staff sought council approval in principle to proceed with invoice processing once ARC eligibility is confirmed or funds reallocated.