Frostburg council approves four resolutions including CSO and paving change orders

Frostburg City Mayor and City Council · August 20, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The Frostburg City Council approved four resolutions by voice vote on Aug. 27, 2025, covering a CSO design change order, two construction test-pit and paving change orders and a routine pretax benefits plan adoption.

The Frostburg City Council approved four resolutions at its Aug. 27 meeting, including change orders for sewer and street projects and a confirmation of the city's pretax medical plan.

Mister O'Brien introduced Resolution 2025-39, a change order related to the combined sewer overflow (CSO) project that included charges described by staff as roughly $4,000–$5,400 for easement specifications and $300 each for 18 easement-related items. Council moved and seconded the item and approved it by voice vote; no recorded roll-call tally was provided in the transcript.

Council then approved Resolution 2025-40, a change order for the roundabout project totaling $8,817.35 to pay for two additional utility test pits conducted by Brutus and Associates to locate utilities ahead of construction. Council members confirmed this expense will be funded from city resources rather than ARC funding and approved the resolution by voice vote.

Resolution 2025-41 reallocated $30,000 among add-alternates under the existing paving contract to cover high-need sections, specifically East First Street and Pritchard Farms driveway and manhole repairs, rather than some previously listed alternates (armory parking and Glendening Park). City staff said the pool parking lot and street-department work remain priorities; the council approved the change order by voice vote.

Finally, Resolution 2025-42 was presented as a formality to document adoption of a Section 125 premium-only pretax medical benefits plan for the plan year beginning July 1, 2025 (document signed June 24, 2025). The council adopted the resolution by voice vote.

All four measures were approved by voice vote with 'Aye' recorded; the meeting transcript does not show a roll-call vote or a numerical tally for any of the resolutions. The council did not take additional conditions or amendments on these items during the meeting.