Mexico City Council approves change orders and an engineering amendment for bridge and stormwater projects
Summary
On Sept. 22, the Mexico City Council approved five resolutions authorizing change orders and an engineering contract amendment across bridge and multiple stormwater projects, citing grant eligibility and local matches; the meeting also included council updates and a public safety complaint about tree work on Holt Street.
Get email alerts on the Infrastructure Change Orders topic
No spam. Unsubscribe anytime.
Mexico City — The Mexico City Council on Sept. 22 approved a package of change orders and an engineering amendment to complete work on several infrastructure projects, including the Pollock Road bridge and multiple stormwater improvement efforts.
Drew Willeford, speaking for city staff, outlined each item and recommended passage. For the Pollock Road bridge closeout, Willeford said that an unexpected drop-off on the southeast quadrant required about 170 feet of guardrail and other adjustments, increasing the project cost by $36,379.84; he said that the addition appears to be grant-eligible and that the city’s local match would be roughly 12.3 percent.
On the Love/Abbott stormwater project, Willeford said the design lacked fiber reinforcement and the city requested a change order to add fiber throughout the work to improve concrete longevity. He estimated the net increase for that addition at $25,470, said the change should be reimbursable through the Department of Natural Resources grant and the American Rescue Plan Act, and explained that DNR allowed cross-usage of funds from two grants awarded for the combined bid package to cover overages.
Willeford also described Change Order 4 for the East Anderson Street stormwater improvement project, listing about 960 linear feet of storm sewer, 1,100 square yards of resurfacing and roughly 1,500 linear feet of curb and gutter. He attributed a $42,983.20 net increase to unforeseen utility conflicts encountered during construction and recommended that this final change be accepted as grant-eligible.
For the Pollock Road culvert replacement, Willeford said crews found a profile difference that produced a pronounced hump in the driving surface. He said the contractor completed corrective work and provided an estimated cost of $43,307; staff recommended submission of the change order to DNR for reimbursement.
Finally, the council approved Amendment 1 with MECO Engineering to add construction administration and inspection services on the Love Abbott stormwater project. Willeford said repeated design revisions caused by unplanned utility conflicts required more oversight; the amendment added $26,000 to pay for inspection and administration.
All measures were moved, seconded and brought up for roll-call response; the responses recorded in the public meeting transcript were affirmative. City staff recommended proceeding with reading by title only and passage for each resolution, noting grant-eligibility in staff comments.
The council also briefly discussed paying claims and acknowledged ongoing construction traffic management on Curtis Street, and members made local announcements about tree plantings and an upcoming "Walk Back in Time" event.
The council adjourned into executive session on a separate motion under Revised Statute of Missouri 610.021 to discuss personnel matters.
What passed (as listed in the meeting record): - Bill 2025-61: Resolution authorizing the city manager to sign Change Order 1 with Lewis Company LLC for the Pollock Road bridge replacement project (grant BROR1191); recommended increase $36,379.84; noted local match ~12.3%. - Bill 2025-62: Resolution authorizing the city manager to sign Change Order 1 with Brown and Root Industrial Services LLC for the Love Abbott stormwater improvement project (DNR grant cited); staff estimated net increase $25,470; reimbursement expected through DNR/ARPA with ~21% local match noted. - Bill 2025-63: Resolution authorizing the city manager to sign Change Order 4 with Sam Gaines Construction Inc. for the East Anderson Street stormwater project (DNR grant cited); staff estimated net increase $42,983.20 due to utility conflicts. - Bill 2025-64: Resolution authorizing the city manager to sign Change Order 1 with TV Dozing and Excavation LLC for the Pollock Road culvert replacement project (DNR grant cited); staff estimated corrective work ~$43,307 and recommended reimbursement submission to DNR. - Bill 2025-65: Resolution authorizing the city manager to sign Amendment 1 with MECO Engineering Inc. for additional construction administration and inspection on the Love Abbott stormwater project; staff recommended authorizing an additional $26,000.
Each item was presented by staff and recommended as grant-eligible; recorded roll-call responses in the public transcript were affirmative. The meeting record does not include formal roll-call tallies with named yes/no votes tied to each individual resolution beyond the prompt-and-response pattern captured during the session.