Fleeterville staff reports progress on 1849 Park, Murchison, Kelly Lane and Lake Pflugerville projects
Summary
Staff updated the Parks and Recreation Commission on multiple capital projects: 1849 Park Phase 2 (62% complete, est. Jan. 21 finish), Murchison Park (74% complete, est. November), Kelly Lane Park (construction contract approved; three pickleball courts; completion May 2026) and design steps for Lake Pflugerville Phase 2 and destination play at Bulls Park.
City parks staff used the Sept. 29 commission meeting to provide a multi-project update on parks work across the city, covering construction progress, upcoming design work and anticipated timelines.
Staff said 1849 Park Phase 2 is 62% complete and includes two 225‑foot baseball fields, one softball‑sized field, parking, field lighting, playgrounds, concessions and restrooms. The team described a tiered layout that staff said will create improved spectator sightlines; staff gave a tentative completion estimate of Jan. 21 but noted construction schedules can…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat