A Bay Construction change order approved for Woodson Road stormwater project

Raytown Board of Aldermen · April 22, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The Board approved a $26,491.59 change order to A Bay Construction Inc. for the Woodson Road stormwater improvement project after staff reported an unexpected sanitary sewer conflict that required enclosing the storm ditch and additional piping, bringing the total not to exceed $378,786.39.

The Raytown Board of Aldermen approved a resolution amending the contract with A Bay Construction Inc. for the Woodson Road stormwater improvement project to cover a $26,491.59 change order, increasing the project total to a not-to-exceed $378,786.39.

Public Works Director Rob Camp told the board crews discovered a shallow sanitary sewer where the new stormwater line was planned, requiring the storm line to be placed below the sewer and the ditch to be enclosed in piping to ensure safety for pedestrians and vehicles. Camp said the change order amount arose from that unanticipated site condition and the need to enclose and pipe the ditch.

Aldermen moved and seconded the resolution after Camp explained the construction challenge and the safety concern for vehicles and pedestrians; the roll call vote approved the change order unanimously. Camp said the project is nearly complete and the additional work will allow staff to finish the job and close out the contract.

The board recorded the amended project total and approved the expenditure for fiscal year 02/2025.