VDOT updates Orange County supervisors on maintenance totals, roundabouts and upcoming public hearings

Orange County Board of Supervisors · September 9, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

VDOT assistant residency administrator Willie Gordon reported routine maintenance metrics (e.g., 184 potholes patched, 16,685 feet of ditching) and project timelines for local roundabout and road work; board members raised concerns about public hearing dates and traffic impacts at shopping-center intersections.

Virginia Department of Transportation assistant residency administrator Willie Gordon delivered a quarterly update to the Orange County Board of Supervisors covering maintenance work, recent project milestones and upcoming public hearings.

Gordon reported maintenance totals for the period, saying the crew "pot patched 184 potholes" and collected "817 cubic yards of debris." He also listed ditching (16,685 linear feet), nearly three miles of shoulder repair, grading of almost 100 center-line miles and other routine work. Gordon described recent pipe work—"replaced 220 linear feet of pipe" and cleaned "690 linear feet of pipe"—and machine brush removal and patching efforts.

On capital projects, Gordon said the Barbersville roundabout has switched to a roundabout configuration and the interior work is expected to be completed in December. He described the Route 601 low-speed curve project as moving forward with an ad date of 2027 and noted the Route 320 (3 and 20) and Route 20/522 projects have public-hearing milestones with dates discussed for Oct. 28 (some participants referenced Oct. 28 while others said Oct. 20; Gordon later confirmed "20 eighth"/Oct. 28 as the public hearing date). Board members expressed concern about scheduling conflicts with the Oct. 28 date for a necessary board meeting and asked VDOT to consider alternatives and to provide a traffic plan for how roundabout configuration will interact with a nearby shopping center.

Supervisors also raised constituent concerns about specific local roads: a request to consider hard surfacing on Route 673 near the dam, a request to complete center-line striping on a two-mile chip-and-seal stretch, and a constituent-requested speed study on Porter Road. VDOT staff agreed to investigate and follow up.

What’s next: VDOT will confirm public-hearing schedules and traffic-control plans, and follow up on the locally-raised maintenance and safety concerns.