Get Full Government Meeting Transcripts, Videos, & Alerts Forever!
Get email alerts on the Land Use Solar topic
No spam. Unsubscribe anytime.
King George supervisors deny Gibson Solar special‑exception after heated public hearing
Summary
After a three‑hour public hearing and extensive board questioning, the King George County Board of Supervisors voted to deny Open Road Renewables’ Gibson Solar special‑exception for roughly 890 acres in the Shiloh District. Supporters cited conservation easements and tax revenue; opponents cited stormwater, tree removal and decommissioning concerns.
Get email alerts on the Land Use Solar topic
No spam. Unsubscribe anytime.
The King George County Board of Supervisors voted July 15 to deny a special‑exception permit for the proposed Gibson Solar facility, a 134‑megawatt project by Open Road Renewables that would have placed about 890 acres of panels and ancillary equipment in the Shiloh District. The public hearing drew more than 50 speakers and more than three hours of debate before the board made the denial.
Staff and the applicants framed the project as a large, conditioned solar installation paired with agricultural grazing. Kelly Leduc, the county’s director of community engagement, said the application included a red‑lined conditions document and an executed conservation easement. Applicant Mike Volpi described the development as “a 134 megawatt utility scale solar facility” with a permanent conservation easement on 1,280 acres and contract commitments for rotational sheep grazing, soil amendments, baseline soil and groundwater testing, decommissioning surety and expanded stormwater protections.
Volpi also pointed to several technical commitments in the proposed conditions: baseline and ongoing soil and groundwater sampling, a decommissioning surety bond updated every five years, and stormwater design provisions that he said were sized beyond state handbook requirements and would include an on‑site responsible land‑disturbing inspector.
Many residents who spoke in opposition said those commitments fell short of the level of protection they want. Speakers raised recurring concerns about the project’s scale and siting — including clear‑cutting more than 500 acres of forest, potential habitat fragmentation, downstream stormwater and sediment impacts, traffic and damage to local roads, and uncertainty about long‑term decommissioning if the operator goes out of business. Several commenters cited the Virginia Tech white paper on solar stormwater issues and asked for third‑party verification of stormwater designs and decommissioning costs. Other speakers questioned the applicant’s outreach, alleging targeted contact methods that made some residents uncomfortable.
Supporters—including several landowners who signed leases and representatives of the North American Land Trust—said the project would generate predictable revenue, preserve larger contiguous tracts under conservation easement, and create grazing access for a young local farmer. Steven Carter of the North American Land Trust told the board the organization had executed a conservation easement tailored to the project and would hold and administer it.
Board members pressed the applicant on specifics including who would own equipment after construction, the sufficiency of decommissioning surety, stormwater basin sizing and inspection, and whether commitments would bind successors and assigns. Applicants pointed to conditions in the permit that state the obligations are binding on successors and to the ordinance’s decommissioning and monitoring language.
After questions and extended debate, a motion to deny the special‑exception application was made and carried by majority vote. The chair declared the motion passed and the application denied.
What happens next: The denial ends the county’s special‑exception review of this application. The applicant may revise and resubmit, appeal, or pursue other administrative remedies; the record and the extensive public comments will be part of the public record. The board did not schedule any further action on this item at the meeting.

