Board approves two auxiliary gym contracts; technology team outlines summer refresh and streaming pilot
Summary
Facilities and technology reports detailed auxiliary gym designs and low bids (combined project estimate about $5.365 million) and technology summer projects including Chromebook/iPad refreshes, 50 smart panels funded in part by a $25,000 WHRO grant, and a pilot camera streaming system for board meetings.
Get email alerts on the Facilities Technology topic
No spam. Unsubscribe anytime.
The Accomack County School Board on June 17 approved contracts for two auxiliary gyms and heard a technology update that included classroom device refreshes and a pilot streaming system for meetings.
Facilities staff presented layouts and bid results for auxiliary gyms at Pungateague and Nandua, noting low bidders and reference checks. The combined project total presented in the slides was approximately $5.365 million; staff recommended moving forward with Athens Building Contracting for Pungateague and Delmarva Veteran Builders for Nandua. The board voted to award the contracts.
Technology staff outlined summer projects: desktop and iPad refreshes, Chromebook and cart maintenance, and the addition of about 50 smart panels in classrooms under the five‑year replacement plan. WHRO provided a $25,000 grant that the district designated toward smart panels. The technology director also described piloting a four‑camera system that can follow speakers and stream the meeting (integrating with Zoom/Meet for public viewing) and listed planned dates for the removal of data center hardware and a backup window in late June/early July.
Why it matters: Facility construction and technology investments affect instructional space, practice facilities and classroom technology availability for the coming school year.
What the board did: The board authorized contracts for the two auxiliary gyms and approved proceeding with project planning; technology projects will proceed over the summer per the five‑year schedule.