O'Fallon approves $4.1M synthetic turf and $10.04M water-treatment contract despite public concerns
Summary
The council approved an amended agreement up to $4.1 million for synthetic turf at Ozzy Smith Sports Complex (8–1) and a contract with CAMEX for reverse-osmosis and water-treatment plant improvements not to exceed $10,035,943 (9–1); public commenters questioned costs and transparency.
Get email alerts on the Capital Projects topic
No spam. Unsubscribe anytime.
The O'Fallon City Council on April 24 approved two high-value capital items after public comment and council discussion.
Resolution 4102025d (dot-1), authorizing ATG Ram Industries LLC to design and install synthetic turf at the Ozzy Smith Sports Complex in an amount not to exceed $4,100,000, was introduced after being removed from the table and approved on an amended motion. During debate Councilmember Ragsdale said she had safety concerns and argued that "artificial turf actually causes more injuries," and she voted no on the measure. Councilmember Smith, citing experience with her daughter's soccer play and rainout reductions, said turf was safer for their uses and supported the resolution. The council approved the amended resolution 8–1.
Later the council introduced and approved Resolution 4 24 2025 d, an agreement with CAMEX Incorporated for reverse-osmosis and general water-treatment plant improvements in an amount not to exceed $10,035,943. Public comment preceding the votes included objections from a city public advocate who described the water project as exceeding earlier estimates and questioned alternate selections and transparency. The council approved the water-treatment contract 9–1.
City Administrator Mike Snowden earlier reported an emergency pump motor repair to Well Number 3 costing $13,765.20 after a storm-related failure; he also thanked staff and volunteers for distributing 23,000 recycling packets and noted a ground-breaking that day for the public works and fleet facility.
Both capital approvals include standard implementation steps: procurement/contract execution and project oversight by public-works and utility divisions. The meeting record shows recorded vote counts and statements by council members opposing or supporting the projects; the items now move to contracting and project initiation.