City reports Briscoe Park water-main tie-in, sewer bore work and fiber conduit completion

Mayor and City Council of Snellville · September 10, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Staff said Briscoe Park completed a water-main connection and will demolish the old line; sewer contractor began a bore under the road to avoid open-cutting Wisteria; Ansco completed conduit work so AT&T can begin fiber cutovers shortly.

City staff told the Sept. 8 work session that multiple infrastructure projects are progressing across Snellville.

Speaker 4 said Briscoe Park completed the water-main connection and crews will demolish the old water main under the building as the project moves toward a slab pour by month's end. On financing, staff reported a positive initial meeting with the Georgia Municipal Association (GMA), which will provide a financing road map.

On sewer work, Speaker 4 said Northland began a sewer bore under the road near United Community Bank to avoid an open cut of Wisteria; casing will be installed to embed the sewer line, with an expected return to the manhole on the far side.

On telecommunications, staff said a company called Ansco completed conduit installation (the reinforced conduit that holds fiber) and that AT&T is expected to start cutovers to new fiber within days or the coming week.

No formal actions or contract awards were recorded during the work-session discussion on Sept. 8; staff said it will keep the council updated as the projects proceed.