Council reviews expanded fire-station design and a $4–5M cost increase; asks staff to trim options

Lakeville City Council · September 23, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Architects presented an updated design for a new combined fire station (consolidating Stations 2 and 4) with seven apparatus bays, training tower and large public/training spaces; the current estimate rose to about $30 million with contingency, prompting council requests to pare public/exterior features and return with refined numbers this fall.

City architects and fire staff presented a substantially developed design for a new combined fire station intended to consolidate Stations 2 and 4. The proposed facility includes seven apparatus bays, a training tower and mezzanine (roughly 4,100 square feet of second-floor training/storage) and a first-floor program of about 39,000 square feet that combines public classroom spaces, administrative offices and cold/hot zones for firefighter health and decontamination.

Staff said the estimate for the project is roughly $30 million, about $4–5 million higher than earlier study estimates. The current cost model includes a 10% contingency rolled into the total; RJM was engaged as construction manager and staff said they are still refining numbers. Councilmembers questioned the scope and cost of public-facing amenities (a large fitness area, multiple conference rooms and a display bay) and asked whether trimming exterior finishes, a conference room or the vehicle-display area could reduce project costs while preserving core operational functions.

Operational design points: Architects explained health-and-wellness design choices intended to separate contaminant-laden areas from living/administrative spaces and to provide dorm-suite-style resident rooms with locker hall access, a wellness room, and apparatus-layout options that can accommodate ambulances in the future. Staff noted the design allows for equipment and ambulance reallocation across other stations if needed.

Council direction: Members asked staff to explore tradeoffs — including reducing public/fitness acreage, removing a display bay and re-examining the number and size of bays — and to return this fall with a narrowed design and updated cost estimates. Several councilors warned that the city has dedicated franchise fees to the project and must balance this build with future renovations to Stations 1 and 3.

No construction contract or final budget was approved at the Sept. 10 meeting; staff said they would return with recommended revisions and firm pricing.