Citizen Portal
Sign In

Get Full Government Meeting Transcripts, Videos, & Alerts Forever!

Get email alerts on the Sewer Reconstruction topic

No spam. Unsubscribe anytime.

Council awards $360,000 sewer reconstruction contract for Third Street stretch

Neptune Beach City Council · August 4, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Council awarded a $360,000 contract to JAX Utilities Management to relay about 70 feet of a failing sanitary sewer line on Third Street to address a localized failure and a depressed travel lane; Councilor Rogers voted no, others voted yes.

Neptune Beach awarded a $360,000 contract to JAX Utilities Management, Inc. to relay roughly 70 feet of gravity sanitary sewer on Third Street. Staff said the targeted run will move the line away from an existing utility pole location, take advantage of an already-mobilized contractor and avoid a larger alternative route estimated at about $791,000.

Public Works described video inspection that showed a splice and settlement had created a depression and structural problem in the pipe that likely requires excavation and replacement rather than lining. The recommended work includes dewatering, traffic control, bypass pumping and removal of excavated materials; the $360,000 alternative was presented as the most cost-effective approach to restoring a structurally sound pipeline in that segment.

On the roll-call vote to award JAX Utilities Management the $360,000 contract, Councilor Rogers voted No; other recorded votes were Yes.